I'll bet they produced the machines with good oversight, communication and
technical consulting with someone who was intimate with the design
process. If those folks are scattered to the four winds, the "restart"
process will not be smooth, efficient of quick even if just for the "why
did they do it that way – lets do it this way (time passes) Oops! Thats
why they did it that way!
Case in point! Challenger accident. NASA violated its own rule that
Lockheed would have to capture 80% of the existin Rockwell launch team in
order to assume the launch processing contract. In my group (Ground Launch
Sequencer and Integration) responsible for the integration of all systme
fucntions and orbiter/gound operations for the last two hours of the
countdown, of the 14 people at Kennedy that worked in Rockwell for me, the
4 more from Marting Marietta and 2 more from USBI that were on my team,
only six stayed and they averaged less than two years on the job. That
was representative of all the Launch team engineering groups. So, that
God-awful day, someone somewhere said the same thing! (Why on earth would
anyone put an ambient temperature limit as a launch commit criteria –
override it – go for launch).
You can't measure experience and continuity in a spreadsheet but it sure
as shooting has an impact on the outcome.
wmc – via Autopilot!