Terminology
9 messages in this thread
Hi, I know this is way off topic but….you folks are plenty smart: Does
anyone know what these abbreviations means as related to general
manufacturing and quality control:
MRP – as used in this sentence: "Establish specifications in
accordance with MRP scheduling requirements."
ASQC Certification
I hate to be pushy but it would be REAL helpful if I could get some ans by
Wednesday (3/25/92) Thanks for any and all assistance. Regards, – al
saveriano –
AL,
Right up my alley! MRP stands for Material Requirements Planning. It is a
system that determines when and how much material your nedd to buy/make
based on your product demand, your current inventory levels, and your WIP
(Work In Process).
Most computerized MRP systems consist of modules:
1. Master Parts Catalog – A database of all the parts you use and
coding that tells the system whether it is a make or a buy part, how
long it takes to make or buy, and, depending on sophistication, lot
sizing, order policies, min-max, reorder point, etc.
2. Bill of Materials – A database of the part/assembly relationship.
What parts go into what assembly and how many it takes.
3. Inventory – A database of your materials in stock.
4. Master Schedule – A database that has your final product (aka: End
Item) schedule (ie: When and how many of your product you want
completed.)- These are called Requirements.
5. Planning – Looks at your master schedule and assigns an order for
each requirement based on data in the Master Parts Catalog (for lot
sizing etc.) Determines a start date for each order (replenishment)
by counting backwards from the Master Schedule date the leadtime in
the Master Parts Catalog. Hence the term — Backwards Scheduling.
Then it looks at Bill of Materials and finds out what you need to
make this assembly, makes their completion date the same as the
assembly's start date. It looks at your inventory balance and
subtracts it out of the orders' quantities it is about to make and
looks at any existing orders to subtract them out, too. As it goes
through this process, called Netting, if it is on a buy item it
stops netting down that chain. For make items, it loops again,
finding the parts that make up this sub-assembly and nets them. It
continues until it has reached the lowest level,which will be all
buy parts.
What I have given you is about $1000 worth of Arthur-Anderson
[ MORE ]
[ continuation ]
consulting. 8) However, it's yours for free. If you wish I can email you
much more info, or email me with your address and I'll mail you info.
My profession, which I'll be leaving in a few weeks <BIG GRIN>, is
Planning and Control Systems for Loral Aerospace- a Defense Contractor. I'm
giving up the exciting world of Planning for Video Production/Editing.
Gosh, I'll even get to use a Toaster!
– via Whap!
Stephen, WOW!!!! THanks a ton! Yes…please..email me whatever you think I
might need for an interview I'll be going on this Thursday morning
(3/26/92). It is for the Quality Assurnace Manager position in a
manufacturing operation. THey will want me to: 1) Develop Statistical
Process Control (SPC) measurements 2) Comduct in-process product evaluation
3) Establidh specifications in accordance with MRP scheduling requirements
THanks again! – al saveriano –
It might help to provide the general category of manufacturing that we are
talking about here (industrial/textiles/electrical/…). Many times the same
acronym means different things.
Al,
I see you just got the MRP defined for you, so here's my two bits.
American Society of Quality Control is the one I'm familiar with, though
there are several organs with the same acronym. Be that as it may, they
all deal with Quality Control, both under manufacturing methods and
testing/design/engineering regimes. ("The Quality is built in before we let
the guy with the hangover screw it up." 8)
Seeing it linked with MRP probably means determining if vendor parts are
up to snuff before acceptance and seeing they're handled/dispatched
properly once on site.
I never was certified through ASQC though I did have to satisy the Air
Force that I knew how to make checkmarks 8). I did put some time in QC
areas for manufacturing routing and discrepancy testing (meaning- making
sure things got done in the proper order and they got checked when
necessary 8)
Doug
Doug, THank you for your input. Do you know HOW you get certified with
ASQC? – al -0
Al,
Sorry, I don't know. I was never certified with them and my job (a
lateral transfer) didn't require it. I had to satisfy a reviewer that I
knew where the proper forms were, and initial a text that contained the
necessary requirements and regulations.(they had to be sure I knew how to
scrawl at least two letter so they knew who to blame in event something
blew up 8) I was more into the production planning end of QC than material
acceptance, testing regimes, etc. stuff.
Like I said, I might be mixing acronyms here. There's a few matching
organizations and some standards that would fit 'em quite nicely. They do,
however, all deal with Quality Control.
If this is part of a job qualification, and you know the job well, ask
about qualifying during any probationary period or tell them you'd accept
the responsibility of becoming certified. From what I've seen, most
companies will hire and assist you in gaining the necessary certification
if you're otherwise qualified.
Doug
Al –
Since the MRP question has been ably answered, I'll answer the other…
ASQC stands for American Society of/for Quality Control. Obviously, if one
is certified by them …